The project schedule will be updated as the PER is developed.

TASK MONTH / YEAR
Prepare Draft PER September 2017-April 2018
Public Hearings: PER, Environmental and Funding May 14, 2018
Final PER completed January 2018
Amend Final PER April 2018
Prepare and submit Grant and Loan Applications (TSEP, RRGL, CDBG, RD, & SRF are potential funding sources) May 2018-July 2018
Notice of Award for TSEP & RRGL funding May 2019
Preliminary Design Fall 2019
Project Bidding Spring 2020
Construction Summer 2020
Project closeout Fall 2020

 

This is a draft schedule and subject to change depending on project development and available funding.