Church Water Main Replacement
The Church Water Main project includes replacement of a segment of leaking water main as part of the City of Thompson Falls continued effort to replace and upgrade the municipal water system. This project includes installation of approximately 1,200 LF of 10” diameter C900 PVC water main, water main fittings, gate valves, and fire hydrant assemblies. The existing water main which has exhibited repeated failures will be capped and abandoned in place. The proposed project will reduce the amount of unaccounted for water in the municipal water system and is an important step in continuing to provide residents access to clean, safe, and reliable drinking water.
Task | Month/Year |
---|---|
Pre-Bid Meeting | Held Sept. 11, 24 at City Hall |
Bid Opening | Held Sept. 24, 24 at City Hall |
Pre-Construction Meeting | Held Oct. 16, 24 at City Hall |
Construction | Began Nov. 4, 24 (Contractor had moved equipment before construction start date) |
Estimated Pipe Installation | Completion by the end of Nov. 24 |
Asphalt Restoration | Completion by Spring of 2025 |
- All funding is from an ARPA Grant
- Thompson Falls Church Street Water – Contractor Cost
- Construction began as of November 4
- Planned for 1 month of construction
- Minimal water service disruption is expected