Schedule:
The project schedule will be updated as the PER Update is completed.
TASK | MONTH / YEAR |
Present Alternatives Analysis to City of Thompson Falls | March 2020 |
Public Hearings: PER, Environmental and Funding | March 9, 2020 & June 8, 2020 |
Final PER completed | May 2020 |
Prepare and submit Grant and Loan Applications (TSEP, RRGL, CDBG & RD are potential funding sources) | May 2020-September 2020 |
Notice of Award for funding | May 2021 |
Preliminary Design | July 2021 |
Project Bidding | Spring 2022 |
Construction | Summer 2022 |
Project closeout | Fall 2022 |
This is a draft schedule and subject to change depending on project development and available funding.